	Project name: Beijing northeast thermoelectric center shenhua guohua gas thermoelectric project 
 
	The construction unit: shenhua guohua (Beijing) gas thermal power co., LTD 
 
	The construction location: Beijing chaoyang district jinzhan village area ma village land use planning in northeast thermoelectric center 
 
	Construction scale: the new 2 * 350 mw gas steam combined cycle power generation heating units (1 set of 2 1 unit), including two grade 9 f350mw two gas turbine, waste heat boiler and 1 steam turbine generating unit;Generating capacity of 951 mw, the total heating capacity is 695 mw, the heating area of 13.9 million square meters, the project covers an area of 90000 square meters, the new construction area of 6.6 square kilometers. The total investment is 3.34888 billion yuan. 
 
	 | 
|  |